PIDA Investment Prospectus
Loading project details...
Energy Egypt, Libya AMU

Egypt and Libya Regional Electrical Interconnection as the First Stage of Completion of the Regional Electrical Interconnection of the North African Region

Current Stage: Feasibility 50%
USD 300.00M

Total Project Cost

USD 0.00M

Investment Required

8

Stakeholders

2

Countries

Project Overview

Description

This stage covers about 165 km from Saloum (Egypt) to Tobruk (Libya) to complete the North Regional Electrical Interconnection. An alternating current (AC) transmission line of about 165 km to exchange a capacity of 1000 megawatts with a voltage of (500/400) kV (Saloum (Egypt) 500 kV – Tobruk (Libya) 400 kV), with a back-to-back 500/400 kV converter station rated 1000 MW.

Objectives

Facilitate the interconnection between the local/national networks/grids of the North African countries by using the combination of alternating current (AC) and direct current (DC) transmission lines, and connections to HV national networks.

Strategic Importance

Critical infrastructure to enhance regional power integration in North Africa, allowing for more efficient use of generation resources and improved energy security.

Technical Specifications

Technology & Design

AC transmission line with back-to-back converter station.

Capacity & Size

1000 MW transmission capacity

Technical Details

An alternating current (AC) transmission line of about 165 km to transmit a capacity of 1000 megawatts with a voltage of (500/400) kV. Saloum (Egypt) 500 kV – Tobruk (Libya) 400 kV, with a back-to-back 500/400 kV converter station rated 1000 MW (two sections rated 500 kV each).

Development, Implementation & Financial Details

Development Timeline

Feasibility studies to be completed by 2024, with project structuring by 2025.

Latest Implementation Updates

UPDATED
Feasibility studies 2023-2024, project structuring 2024-2025, construction 2026-2028, operation from 2028.
2024-07-04: Egypt & Libya agreed to boost their power grid connection – https://libyareview.com/45740/egypt-libya-to-boost-power-grid-connection/
2025-09-02 — State Information Service: Egypt plans to lift total export capacity to ~3.9 GW in FY 2025/26, with upgrades across interconnections including Libya; detailed Libya tendering TBD. [https://www.sis.gov.eg/Story/212799/Egypt-to-double-renewable-energy-investments-in-FY-2025-2026?lang=en-us]

Financing Structure

The project is likely to be financed through a combination of public investment from both countries and potential support from regional development banks.

Capital Structure

80% public funding, 20% from development finance institutions

Project Timeline

Start Date

January 2024

Expected Completion

December 2028

Development Timeline

Feasibility studies to be completed by 2024, with project structuring by 2025.

Project Status History

Status 2020

Pre-Feasibility

Status 2022

Pre-Feasibility

Status 2024

Feasibility

Additional Project Details

Preparation Funding Gap

USD 7.50M

Construction Timeline

Construction expected to take 2-3 years after financial close.

Legal & Financial Advisors

To be appointed

Market Analysis

Market Analysis

Growing demand for power in both countries, with opportunities for complementary peak load sharing.

Market Demand

Both countries face seasonal demand variations that can be partially addressed through power exchange.

Key Stakeholders

Project Sponsor

Egyptian Electricity Transmission Company, General Electricity Company of Libya

Key Parties

Egyptian Electricity Transmission Company, General Electricity Company of Libya

Investors

Governments of Egypt and Libya, potential regional development banks

Contractors & Operators

To be determined through competitive procurement

Risk Assessment

General Risk Assessment

Political risks due to regional instability, technical coordination challenges, potential construction delays.

Regulatory Risks

Established regulatory frameworks in both countries, though coordination mechanisms may need strengthening.

Impact Assessment

Environmental Impact

Limited environmental impact expected as the project follows existing infrastructure corridors.

Social Impact

Enhanced energy security, potential economic benefits from trade in electricity.

Investment Opportunities

Private Sector Opportunities

The private sector could invest in the project although this will most likely be undertaken by the two national power utilities. The project will seek to have a procurement preference for women.

Next Steps & Agreements

Next Steps

Complete feasibility studies, finalize technical design, secure financing

Offtake Agreements

Power exchange agreements to be established between the two national utilities.

Contact Information

Ministry of Electricity and Renewable Energy (Egypt), Ministry of Electricity and Renewable Energy (Libya)