PIDA Investment Prospectus
Loading project details...
Water Madagascar SADC

Water Supply Project in Antanambao Manampotsy

Current Stage: Pre-Feasibility 37.5%
USD 88.00M

Total Project Cost

USD 0.00M

Investment Required

4

Stakeholders

1

Countries

Project Overview

Description

Development of water infrastructure and resource management interventions in Antanambao Manampotsy area of Madagascar.

Objectives

Project Objectives:
- Improve access to clean drinking water
- Protect community water sources
- Implement climate adaptation measures
- Develop sustainable infrastructure
- Enhance water resource monitoring
- Reduce waterborne diseases
- Support agricultural productivity

Strategic Importance

Critical for improving water access and climate resilience in the region

Technical Specifications

Technology & Design

Cascading lakes and retention dams system

Capacity & Size

Service capacity for 71,910 residents

Technical Details

Infrastructure:
- Water retention systems
- Distribution networks
- Treatment facilities

Development, Implementation & Financial Details

Development Timeline

Project Schedule:
- Preparation: Jan-Nov 2025
- Procurement: Dec 2025-Apr 2026
- Construction: May 2026-Oct 2027

Latest Implementation Updates

UPDATED
Project completion targeted for October 2027
2025-08-13: Listed in the AU-AIP 2025 Investment Pipeline during the Cape Town summit (project fiche showcased to financiers). — https://aipwater.org/aip-water-investment-summit-2025/investment-pipeline/
2024-11-30: Government project brief sets 2025 preparation calendar (Jan–Nov 2025), procurement Dec 2025–Apr 2026, works May 2026–Oct 2027 (schedule reaffirmed at 2025 events). — https://au-pida.org/events/wp-content/uploads/2024/11/PROJET-DALIMENTATION-EN-EAU-A-ANTANAMBO-MANAMPOTSY-REGION-DATSINANANA1.pdf

Project Timeline

Start Date

January 2025

Expected Completion

October 2027

Development Timeline

Project Schedule:
- Preparation: Jan-Nov 2025
- Procurement: Dec 2025-Apr 2026
- Construction: May 2026-Oct 2027

Project Status History

Status 2020

Project Definition

Status 2022

Project Definition

Status 2024

Pre-Feasibility

Additional Project Details

Construction Timeline

May 2026 to October 2027

Market Analysis

Market Demand

71,910 residents in project area

Key Stakeholders

Project Sponsor

Government of Madagascar

Key Parties

Ministry of Water, Sanitation, and Hygiene

Risk Assessment

General Risk Assessment

Primary risks in funding and implementation

Regulatory Risks

Requires clear regulatory framework

Impact Assessment

Environmental Impact

Environmental impact studies needed

Social Impact

Will improve water access for 71,910 residents

Investment Opportunities

Private Sector Opportunities

Private sector opportunities in infrastructure and operations

Next Steps & Agreements

Next Steps

Complete project design and secure funding