Total Project Cost
Investment Required
Stakeholders
Countries
Project Overview
Description
Development of water infrastructure and resource management interventions in Antanambao Manampotsy area of Madagascar.
Objectives
Project Objectives:
- Improve access to clean drinking water
- Protect community water sources
- Implement climate adaptation measures
- Develop sustainable infrastructure
- Enhance water resource monitoring
- Reduce waterborne diseases
- Support agricultural productivity
Strategic Importance
Critical for improving water access and climate resilience in the region
Technical Specifications
Technology & Design
Cascading lakes and retention dams system
Capacity & Size
Service capacity for 71,910 residents
Technical Details
Infrastructure:
- Water retention systems
- Distribution networks
- Treatment facilities
Development, Implementation & Financial Details
Development Timeline
Project Schedule:
- Preparation: Jan-Nov 2025
- Procurement: Dec 2025-Apr 2026
- Construction: May 2026-Oct 2027
Latest Implementation Updates
UPDATED2025-08-13: Listed in the AU-AIP 2025 Investment Pipeline during the Cape Town summit (project fiche showcased to financiers). — https://aipwater.org/aip-water-investment-summit-2025/investment-pipeline/
2024-11-30: Government project brief sets 2025 preparation calendar (Jan–Nov 2025), procurement Dec 2025–Apr 2026, works May 2026–Oct 2027 (schedule reaffirmed at 2025 events). — https://au-pida.org/events/wp-content/uploads/2024/11/PROJET-DALIMENTATION-EN-EAU-A-ANTANAMBO-MANAMPOTSY-REGION-DATSINANANA1.pdf
Project Timeline
Start Date
January 2025
Expected Completion
October 2027
Development Timeline
Project Schedule:
- Preparation: Jan-Nov 2025
- Procurement: Dec 2025-Apr 2026
- Construction: May 2026-Oct 2027
Project Status History
Status 2020
Project Definition
Status 2022
Project Definition
Status 2024
Pre-Feasibility
Additional Project Details
Construction Timeline
May 2026 to October 2027
Market Analysis
Market Demand
71,910 residents in project area
Key Stakeholders
Project Sponsor
Government of Madagascar
Key Parties
Ministry of Water, Sanitation, and Hygiene
Risk Assessment
General Risk Assessment
Primary risks in funding and implementation
Regulatory Risks
Requires clear regulatory framework
Impact Assessment
Environmental Impact
Environmental impact studies needed
Social Impact
Will improve water access for 71,910 residents
Investment Opportunities
Private Sector Opportunities
Private sector opportunities in infrastructure and operations
Next Steps & Agreements
Next Steps
Complete project design and secure funding