PIDA Investment Prospectus
Loading project details...
Energy Botswana, Namibia, Zambia, Zimbabwe SADC

Zimbabwe Zambia Botswana Namibia (ZIZABONA) Interconnector Project

Current Stage: Structuring 62.5%
USD 240.00M

Total Project Cost

USD 0.00M

Investment Required

9

Stakeholders

4

Countries

Project Overview

Description

The ZIZABONA transmission project consists of the development, financing, construction and operation of new transmission facilities in Zimbabwe, Zambia, Botswana and Namibia to facilitate the creation of a western transmission corridor in the Southern African Power Pool to decongest the central corridor. The construction is 422 km of transmission interconnectors in Zimbabwe (Hwange) – Zambia Livingstone (Mukuni) – 101 km (Hwange to border) and 14km (border to Mukuni), Zimbabwe (Victoria Falls) – Botswana (Pandamatenga) – 76 km, Zambia (Mukuni) – Namibia (Zambezi) – 231 km. All lines will be constructed at 400 kV, with initial operation at 330kV and initially targeting to transfer 300 MW.

Objectives

Provide an alternative electrical power transmission in the region and decongest the existing central transmission corridor congest the existing central transmission corridor that passes through Zimbabwe, thus boosting electricity trading among Member States. Interconnect the four countries. Create an alternative wheeling path between North and South and Decongest the Central Transmission Corridor for enhanced power trade among SADC countries.

Strategic Importance

Strategic regional transmission project to enhance power trading capacity and system reliability in Southern Africa.

Technical Specifications

Technology & Design

Regional transmission interconnection with 400 kV capacity.

Capacity & Size

300 MW initial transfer capacity

Technical Details

All lines will be constructed at 400 kV, with initial operation at 330kV and initially targeting to transfer 300 MW.

Development, Implementation & Financial Details

Development Timeline

Project structuring to be completed by 2024, with financial close targeted for 2025.

Latest Implementation Updates

UPDATED
Project structuring 2023-2024, financial close 2025, construction 2026-2028, operation from 2028.
2024-01-23: AfDB procured consultancy to update ZIZABONA feasibility & ESIA studies – https://www.afdb.org/en/documents/contract-awards-zizabona-project-preparation-support-pps-under-africa-energy-transition-catalyst-program-updates-feasibility-and-esia-studies-pern

Financing Structure

The project is expected to be financed through a combination of public funding from the participating utilities and support from development finance institutions.

Capital Structure

75% debt, 25% equity

Project Timeline

Start Date

January 2023

Expected Completion

December 2028

Development Timeline

Project structuring to be completed by 2024, with financial close targeted for 2025.

Project Status History

Status 2020

Structuring

Status 2022

Structuring

Status 2024

Structuring

Additional Project Details

Preparation Funding Gap

USD 5.00M

Construction Timeline

Construction expected to take 2-3 years after financial close.

Legal & Financial Advisors

To be appointed

Market Analysis

Market Analysis

Growing power trade in the SAPP region, with need for additional transmission capacity to reduce congestion.

Market Demand

Existing central corridor is congested, limiting power trading opportunities in the region.

Key Stakeholders

Project Sponsor

ZIZABONA Project Management Unit

Key Parties

Namibian Power Utility (NamPower), Zimbabwe Electricity Supply Authority (ZESA), Zambia Electricity Supply Corporation (ZESCO), Botswana Power Corporation (BPC)

Investors

The four national utilities, development finance institutions

Contractors & Operators

To be determined through competitive procurement

Risk Assessment

General Risk Assessment

Coordination challenges among multiple countries, financing risks, potential construction delays.

Regulatory Risks

Regulatory frameworks in place but require harmonization across the four countries.

Impact Assessment

Environmental Impact

Limited environmental impact expected as the transmission lines follow existing corridors where possible.

Social Impact

Enhanced energy security, support for economic development, potential for increased regional cooperation.

Investment Opportunities

Private Sector Opportunities

Boost of tourism sectors in the border towns of Victoria falls and Kazungula through increased and reliable power supply, a sector which favours women participation.

Next Steps & Agreements

Next Steps

Complete project structuring, secure financing commitments, finalize environmental approvals

Offtake Agreements

Transmission service agreements to be established among the participating utilities.

Contact Information

Project Management Unit, ZIZABONA Project