PIDA Projects Performance Dashboard

Programme for Infrastructure Development in Africa
Default performance calculation: 2022 → 2024

Dashboard Overview

About This Dashboard

This dashboard tracks the implementation progress of PIDA projects across sectors, displaying performance metrics based on the 2022 → 2024 interval by default. It shows project stages (with counts), global performance scores, and performance breakdowns.

Performance Score Formula: ((Improved + 0.5 × Same) / (Improved + Same + Declined)) × 100.

How to Use
  • Use the dropdown filters to narrow projects by Sector, Status, REC, or Region.
  • Click on any project row to view detailed information and the implementation timeline.
  • The progress indicators (green ✓, orange −, red ×) reflect changes in project stages.
  • Click on a sector card to instantly filter projects by that sector and view its performance.
  • Express Interest or share project details via the provided buttons.
Global Performance Score

The Implementation Performance score indicates how effectively projects advance. A high score (green) means strong progress, while lower scores (orange/red) indicate projects that have stalled.

Improved (39)
Same (30)
Declined (0)
Formula: ((Improved + 0.5 × Same) / Total with status) × 100
Project Implementation Stages:
S0 Enabling Environment 1
S1 Project Definition 9
S2A Pre-Feasibility 13
S2B Feasibility 23
S3A Project Structuring 11
S3B Transaction Support 4
S4A Implementation - Tendering 4
S4B Implementation - Construction 4
Filter Projects
Total Projects
69
Projects Advancing
39 +57%
Countries Involved
55
Implementation Performance
78%
Low Medium High
39 30 0
Total Project Cost
$124,524.77 M
Energy
18
(26% of projects)
Low Medium High
11 7 0
Transport
25
(36% of projects)
Low Medium High
11 14 0
Water
15
(22% of projects)
Low Medium High
6 9 0
ICT
11
(16% of projects)
Low Medium High
11 0 0
Project Name Sector Sub-Sector Development Stage Progress Status 2020 Status 2022 Status 2024 Cost (USD M) Investment Ask (USD M)
3,050 MW Mambillla Hydroelectric Power Project Energy Hydropower Project Structuring S3A S3A S3A 5,800.00 0.00
Abidjan -- Ouagadougou -- Niamey -- Cotonou -- Lomé Regional Rail Loop Project Transport Railway Infrastructure Project Definition S2B S1 S2A 9,600.00 0.00
Abidjan-Lagos Corridor Highway Development Project Transport Highway Infrastructure Feasibility Stage S3A S2A S3A 15,600.00 0.00
Akagera River Transport Transport Water Transport Feasibility Stage S1 S2A S2B 180.00 0.00
Angololo Multipurpose Water Resources Development Project Water Multi-purpose Water Resources Project Structuring S2B S2B S3A 136.00 0.00
Baynes Hydropower Project Energy Hydropower Structuring (S3A) S2B S2A S3A 1,300.00 0.00
Beira Port Development Transport Port Pre-Feasibility Stage S3A S2A S2A 450.00 0.00
Bousalemn Highway in Tunisia at the Algerian Border Transport Highway Infrastructure Transaction Support S3A S3A 81.47 0.00
Construction of 287 MW Ruzizi IV Hydropower Project Energy Hydropower Feasibility (S2B) S2A S2A S2B 712.00 0.00
Construction of a Bridge over the Oubangui River Transport Road Infrastructure Pre-Feasibility S1 S2A S2A 215.00 0.00
Construction of a Petroleum Jetty and Associated Storage Facilities at Albion Transport Port Infrastructure Feasibility S2A S2B 385.00 0.00
Construction of Amilcar Cabral submarine cable system ICT Submarine Cable Transaction Support & Financial Close S1 S2A S3B 74.50 0.00
Construction of Standard Gauge Railway from Mtwara/Mbamaba - Liganga to Mchuchuma Transport Railway Infrastructure Pre-Feasibility S2A S2A 2,150.00 0.00
Construction of Standard Gauge Railway: Mombasa -- Nairobi -- Malaba -- Kampala -- Kigali line Transport Railway Infrastructure Financial Close S3A S3B S4A 13,800.00 0.00
Construction of the Central Corridor Standard Gauge Railway Transport Railway Infrastructure Financial Close S2B S3B S4A 7,500.00 0.00
Construction of the Dam and Development of the Palambo Hydroelectric Plant Water Multi-purpose Dam Feasibility stage S2A S2B S2B 0.00 0.00
Continental Africa Water Investment Support Programme (AIP) Water Transboundary Water Investment Project Definition S0 S1 S1 1,860.00 0.00
Continental Seamless Airspace in Africa in the Context of SAATM Transport Air Transport Pre-Feasibility S2A S2A 420.00 0.00
Dawa River Multi-purpose Dam Water Multi-purpose Dam Project Definition S1 S1 S1 603.50 0.00
Development of Data Centre Infrastructures Underpinning the Digital Economy ICT Data Centers Project Definition S0 S0 S1 9.00 0.00
Development of the BAC and LOTEMO Hydroelectric Sites on the Lobaye River, and Related Works in CAR Energy Hydropower Feasibility S2B S2B S2B 406.50 0.00
Development of the Booue and Tsengue-Leledi Hydroelectric Sites and Associated Transmission Lines Energy Hydropower Feasibility (S2B) S3B S2A S2B 1,784.10 0.00
Development of the Chollet Hydroelectric Site and Associated Transmission Lines Energy Hydropower Feasibility S2A S2B 2,009.00 0.00
Doubling of the RN06 between Mascara and Bechar and the RN50 between Bechar and the Algerian-Mauritanian Border Transport Road Infrastructure Financial Close S3A S4A S4A 1,850.00 0.00
Eastern Africa Green Power Transmission Network Project 6 - Guba (Ethiopia)-Khartoum (Sudan) Energy Transmission Structuring (S3A) S2B S2A S3A 850.00 0.00
Egypt and Libya Regional Electrical Interconnection as the First Stage of Completion of the Regional Electrical Interconnection of the North African Region Energy Transmission Feasibility (S2B) S2A S2A S2B 300.00 0.00
Egypt and Sudan Electrical Grid as the First Stage of the Continental Electrical Interconnection Energy Transmission Feasibility (S2B) S1 S1 S2B 2,200.00 0.00
El Fasher -- Kabkabiya -- El Geneina -- Adre Road Corridor Transport Road Infrastructure Financial Close S4A S4A 295.00 0.00
Establishment of a Navigational Line between Lake Victoria and the Mediterranean Sea (VICMED) Transport Water Transport Pre-Feasibility S2B S2A S2A 1,250.00 0.00
Extension of National ICT Broadband Backbone (NICTBB) to DRC by construction of optical fibre cable across Lake Tanganyika and point of presences (PoPs) for providing connectivity with DRC ICT Fiber Optic Pre-feasibility Stage S1 S1 S2A 4.00 0.00
Extension of National ICT Broadband Backbone (NICTBB) to Mozambique ICT Fiber Optic Feasibility Stage S1 S2A S2B 4.00 0.00
Feasibility and In-depth Studies on the Development of Lake Chad Water Water Resource Management Feasibility Stage S1 S1 S2B 21.60 0.00
Fomi Multipurpose Dam Development Project Water Multi-purpose Dam Feasibility Stage S3B S2B S2B 55.20 0.00
Grand INGA Phase 1 Energy Hydropower Transaction Support and Financial Close S3B S3B S3B 14,000.00 0.00
Highway Linking the Terminal Part of the Fez-Oujda Highway to the Algerian East-West Highway Transport Road Infrastructure Pre-Feasibility S2A S2A 145.00 0.00
Implementation of an ECOWAS Regional Internet Exchange Points ICT Internet Exchange Feasibility Stage S0 S0 S2B 0.30 0.00
INGA 3 Transmission Interconnector Energy Transmission Enabling Environment and Needs Assessment S0 S0 S1 3,564.00 0.00
Integration of Electrical Networks between Inga-Cabinda and Pointe Noire Energy Transmission Transaction Support & Financial Close S3B S2B S3B 160.00 0.00
Interconnection of Member States' Broadband Networks ICT Broadband Networks Project Definition S0 S0 S1 0.30 0.00
Juba - Nairobi Fiber Optic Link ICT Fiber Optic Feasibility Stage S0 S1 S2B 4,500.00 0.00
LAPSSET Crude Oil Pipeline Energy Oil & Gas Project structuring/Project Definition S3A S1 S1 3,064.00 0.00
LAPSSET Railway Project Transport Railway Infrastructure Feasibility Stage S2A S2A S2A 12,000.00 0.00
Lesotho Highlands Water Project Phase II Water Water Transfer Construction S3A S4B S4B 2,600.00 0.00
Lesotho-Botswana Water Transfer Project Water Transboundary Water Resource Management Feasibility Stage S2A S2B S2B 2,530.00 0.00
Libyan Alternative Freeway Transport Road Infrastructure Project Structuring S3A S3A S3A 2,850.00 0.00
Louga Hydroelectric Power Plants 1 and 2 (246 MW) Energy Hydropower Transaction Support & Financial Close (S3B) S2A S2A S3B 613.00 0.00
Luapula Hydropower Project Energy Hydropower Feasibility S2B S2B S2B 540.00 0.00
Maritime Link Between the Comoros Islands Transport Port Project Structuring S0 S3A S3A 88.00 0.00
Masaka - Mwanza Transmission Line Project Energy Electrical Transmission Project Structuring S2B S2B S3A 325.00 0.00
Mobilisation and Transfer of Water from Bria Dam to Lake Chad Water Water Transfer Pre-Feasibility S2A S2A S2A 25.60 0.00
Modernisation of the RN01 (Trans-Saharan) between Ghardaia and Tamenrasset Transport Road Infrastructure Under Construction S3A S3A S4B 1,250.00 0.00
Noordoewer/Vioolsdrift Dam Water Water Resource Development Feasibility stage S2B S2B S2B 501.50 0.00
Noumbiel Multipurpose Dam Water Multi-purpose Dam Pre-feasibility S2A S2A S2B 169.00 0.00
Operationalisation of São Tomé and Príncipe Hydrometric Stations Water Water Resource Management Feasibility Stage S3A S2A S2B 1.50 0.00
Praia-Dakar Shipping and Maritime Services Project Transport Maritime Transport Feasibility S2B S2A S2B 175.50 0.00
Praia-Dakar-Abidjan Multimodal Transport Corridor Transport Road Pre-Feasibility Stage S3A S2A S2A 975.00 0.00
Project for the Construction of the Bridge Over the Ntem River Transport Road Infrastructure Under Construction S3A S4B 75.00 0.00
Rehabilitation and Creation of Cross-border Centres as Multi-Service Logistics Zones Transport Border Infrastructure Feasibility S2A S2B 185.00 0.00
Rehabilitation, Modernisation and Improvement of the Services of the Trans-Maghreb Railway Line Transport Railway Infrastructure Project Definition S2B S1 S1 1,250.00 0.00
Rihaid El Birdi -- Om Dafug Road Corridor Transport Road Infrastructure Feasibility S2B S2A S2B 175.00 0.00
SADC Regional Carrier-Neutral Data Centre ICT Data Centers Project Definition S0 S0 S1 1.00 0.00
Sudan Section of the Fiber Optic Connectivity Component of the Port Sudan to Douala Corridor ICT Fiber Optic Pre-feasibility Stage S1 S1 S2A 55.00 0.00
Support Programme for the Facilitation of Transport by Inland Waterways, Securing River Navigation and the Sustainable Management of Water Resources in the Congo Basin Water Water Transport Enabling Environment and Needs Assessment S0 S0 S1 93.80 0.00
Trans-Saharan Optic Fibre Broadband Project ICT Fiber Optic Construction Stage S1 S1 S4B 58.00 0.00
Transborder Submarine Fiber PoPs, Regional Smart Hub Facility and Data Centre ICT ICT Infrastructure Project Structuring S2A S2B S3A 70.00 0.00
Using Solar and Wind Energy to Extract Groundwater in Pastoral Wells Water Ground Water Management Enabling Environment and Needs Assessment S1 S0 S0 0.40 0.00
WAPP Regional Solar Power Park Project in Mali Energy Solar Feasibility S2B S2B S2B 250.00 0.00
Water Supply Project in Antanambao Manampotsy Water Water Supply Pre-feasibility S1 S1 S2A 88.00 0.00
Zimbabwe Zambia Botswana Namibia (ZIZABONA) Interconnector Project Energy Transmission Project Structuring S3A S3A S3A 240.00 0.00